Capital Projects

Post

GRC 2020 General Case (2022-24)

The General Rate Case approved June 29, 2023, invests over $22 million in the Barstow water system. The new rates are being invested in your service area’s waste disposal systems, power loss prevention at treatment plants, water tank upgrades, and backup power equipment.

GRC 2023 General Case (2025-27)

The rates proposed for 2025-2027 will provide customers with long-term value by investing over $27.9 million in proactive capital investments and maintenance of local water infrastructure essential to the delivery and treatment of reliable, quality water. Investments in the Barstow Service Area include, but are not limited to, water distribution projects, seismic and structural upgrades to two reservoirs, a treatment plant and a well, backup generators needed for uninterrupted treatment and delivery of water in the event of power outages, natural disasters and to reduce the strain on the electrical grid and the replacement of aging infrastructure including water mains, electrical works, pumping and purification and safety equipment.

Current & Upcoming Projects

Agarita Reservoir Upgrades

Location: 34976 Agarita Ave., Barstow, CA.

Project Timeline:
January 8, 2024 – June 2024

Working Hours:
Monday – Friday (No weekends or holidays)
7:00 a.m. – 5:00 p.m.

Construction crews will work to:

  • Replace new tank coating, repair the tank and perform safety upgrades.

This project will ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice.

Recently Completed Projects

Beryl Plant Demolition Project

Location: 34574 H Street Barstow

Project Timeline:
September 2022 – Mid-December 2022

Working Hours:
Monday – Friday (No weekends or holidays)
7 a.m. – 5 p.m.

Construction crews worked to:

  • Tank demolition
  • Install new services
  • Install fire hydrant.

The streets will remain open to traffic during the construction period but traffic and parking may be restricted and access to driveways may be limited for short durations of time. The construction crews will make every effort to keep dust to a minimum. Please expect an increased level of noise during the construction period. Weekly activities such as trash pick-up will not be interrupted. As the new services are being installed minor disruptions due to the shut-down in water services will happen. This step is necessary to protect public health and to ensure compliance with the Waterworks Standards. Following the disinfection period, crews will flush the chlorinated water and any construction-related sediment from the pipelines. Crews will dechlorinate the water before discharge. Generally, as underground activities are completed the crews will progress to the next underground sections and come back near the end of the project to perform landscape and hardscape restoration as well as perform final street paving.

View the Construction Notice.

Irwin Transmission Main Project

Location: Irwin Road from Gabilan Street to Barstow Road

Project Timeline:
December 20, 2021 – Late January 2022

Construction crews worked to:

  • Install 5,700 ft. of new water pipe

View the Construction Notice.

outline of Crooks Ave Barstow Project

Barstow
Crooks Ave. and Pierce Ave.

Project Timeline:
July 5, 2017 – August 18, 2017

Construction crews worked to:

  • Install 1,700 ft. of new water pipe
  • Install 10 new service lines
  • Install 4 fire hydrants

View the Construction Notice.
 

outline of Barstow Avenues A, B & C Project

Ave. A, Ave. B, & Ave. C
Between Flora Ave. and Keith St.

Project Timeline:
May 8, 2017 – June 20, 2017

Working Hours:
7 a.m. – 4:30 p.m.

Construction crews worked to:

  • Install 450 ft. of new water pipe
  • Install 5 new service lines
  • Install 1 fire hydrant

View the Construction Notice.
 

outline of Barstow Heights Project

Barstow Heights
Highview Ave., N St. and O St.

Project Timeline:
November 7, 2016 – mid-April 2017

Working Hours:
7 a.m. – 4 p.m.

Construction crews worked to:

  • Install 11,500 ft. of new water pipe
  • Install 72 new service lines
  • Install 13 fire hydrants

View the Construction Notice.
 

outline of Barstow Rimrock Rd Project

Barstow
Rimrock Rd., Armory Rd., G St. and D St.

Project Timeline:
September 9, 2016 – January 2017

Working Hours:
7 a.m. – 4 p.m.

Construction crews worked to:

  • Install 11,500 ft. of new water pipe
  • Install 78 new service lines
  • Install 12 fire hydrants

View the Construction Notice.