Capital Projects
2023 General Rate Case (2025-27)
The rates adopted for 2025-2027 will provide customers with long-term value by investing over $6.1 million in needed capital investments and maintenance of local water infrastructure essential to the delivery and treatment of reliable, quality water.
Investments in the Bay Point Service Area include but are not limited to, investment in water supply, distribution improvements, new pumping plant equipment, replacement of aging water mains, equipment for pipeline repair and replacement, analysis of the service area’s aging water infrastructure, and a feasibility study for the use of recycled water. As part of our commitment to reliability and public safety, Golden State Water proactively invests in upgrading and maintaining its fire hydrants.
For frequently asked questions about the rate-making process, click here.
Learn about the infrastructure investments in the water system serving your community’s homes and businesses: 2023 GRC Infrastructure Investments - Bay Point.
Current & Upcoming Projects
Recently Completed Projects
Hill Street Plant
Investment:
$435,000
Project Timeline:
July 6, 2018 – March, 2020
Working Hours:
TBD
Project Update:
Golden State Water crews have completed site grading and erected
the building. Crews will begin work on the interior of the
building in January 2020.
Construction crews will work to construct a new control room and warehouse facility.
This project will ensure Golden State Water can continue providing reliable water service to local customers.