Capital Projects

Post

GRC 2020 General Case (2022-24)

The General Rate Case approved June 29, 2023 invests over $44 million in the Central Basin West Customer Service Area. The new rates are being invested in your service area’s new wells, manganese treatment, treatment plant upgrades, reservoir upgrades, and backup power equipment.

GRC 2023 General Case (2025-27)

The rates proposed for 2025-2027 will provide customers with long-term value by investing over $43.8 million in proactive capital investments and maintenance of local water infrastructure essential to the delivery and treatment of reliable, quality drinking water. Investments in the Central Basin West Service Area include but are not limited to constructing a new well to improve water supply reliability; upgrading water distribution infrastructure, water treatment facilities, and systemwide technology that monitors and controls the water system; installing backup generators needed for uninterrupted treatment and delivery of water in the event of a power outage or a natural disaster; replacing aging water mains, meters, pumps, and water purification equipment.

Current & Upcoming Projects

Recently Completed Projects

Crafton Avenue Area Main Replacement

Job Location: Crafton Ave, Alamo Dr., Beck Ave., Bell Ave., Florence Ave., Gage Ave., Nelson Dr., Nevada, Southall Lane, Walker Ave & Wilcox Ave.

Project Timeline:
January 2023 – July 2023

Working Hours:
Monday – Friday (excluding holidays)
7:00 a.m. – 5:00 p.m.

Construction crews will work to:

  • Install 8,000LF of 8” PVC

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice.

Domestic Water Service Irrigation Installation

Job Location: 6619 King Avenue, Units A-G

Project Timeline:
January 2023 – February 2023

Working Hours:
Monday – Friday (excluding holidays)
7 a.m. – 5 p.m.

Construction crews will work to:

  • Install new (7) 1” domestic water service & (1) 1” Irrigation

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice.

Installation of New Water Main, Fire Hydrants and Customer Services

Prince Ave, John Ave, Mary Ave, Plevka Ave, Firestone Blvd, Compton Ave, 87th PL, 89th ST & 92nd ST.

Investment: 
Over $3,200,000

Project Timeline:
June 13, 2022 – February 2023

Working Hours:
Monday – Friday (excluding holidays)
7 a.m. – 5 p.m.

Construction crews will work to:

  • Install approx. 7,400 LF of 8” new main
  • Install 12 fire hydrants
  • Install 231 services.

The installations listed above are a replacement to old installations that have served their useful life.  The project will upgrade and improve the water distribution system pipeline, services and fire hydrants, to continue the reliable and safe delivery of potable water well into the future.

View the Construction Notice.

Walnut Drive Area Main Replacement
Walnut Dr., Florence Ave, Alameda Ave, Crockett Blvd, 73rd ST, 74th ST, 75th ST, 76th ST, 77th ST & 78th ST.

Investment: 
$4,500,000

Project Timeline:
October 8, 2021 – February 5, 2023

Working Hours:
Monday – Friday (excluding holidays)
7 a.m. – 4 p.m.

Construction crews will work to:

  • Install approx. 13,600 LF of 8” & 12” new main
  • Install 24 fire hydrants
  • Install 457 services.

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice.

project map

Otis Ave. Area Main Replacement
Otis Ave between Florence Ave and Gage Ave, Prospect Ave & King Ave between Gage Ave and Bell Ave, Nevada St. & Acacia St. between Prospect Ave and Mayflower Ave.

Investment: 
$2,860,000

Project Timeline:
November 30, 2020 – April 30, 2021

Working Hours:
Monday – Friday (excluding holidays)
7 a.m. – 4 p.m.

Construction crews worked to:

  • Install  4,100 feet of 8” new main
  • Install 3,000 feet of 12″ new main
  • Install 15 fire hydrants
  • Install 231 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice.

Project Map

Lucille Ave. Area Main Replacement
Lucille Ave, Nevada St, Acacia St, Riverside, Ave, Gifford Ave, and Clarkson Ave.

Investment: 
$1,740,000

Project Timeline:
September 8, 2020 – February 2021

Working Hours:
Monday – Friday (excluding holidays)
7 a.m. – 4 p.m.

Construction crews worked to:

  • Install  4,785 feet of 8” new main
  • Install 14 fire hydrants
  • Install 122 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice .

Sample Station Replacement
Los Angeles, Bell, Bell Gardens and South Gate

Project Timeline:
Feb. 19, 2020 – March 25, 2020

Construction crews will work to replace 30 sample stations.

This project will ensure Golden State Water can continue taking reliable and accurate samples in the local distribution system for water quality testing.

outline of Hollydale System Project

Main Street Area Main Replacement
Hollydale System

Investment: 
$1,322,500

Project Timeline:
August 16, 2018 – November 2019

Working Hours:
City of South Gate
Monday – Friday (excluding holidays)
8 a.m. – 4 p.m.

City of Paramount
Monday – Friday (excluding holidays)
7 a.m. – 4 p.m.

Construction crews worked to:

  • Install 5,400 feet of pipeline
  • Install 14 fire hydrants
  • Install 122 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the construction notice.
 

outline of Florence-Graham Project

Florence-Graham
80th St., 82nd Pl., 83rd St., 84th St., 85th St., Beach St., and Bell Ave.

Investment:
$2.17 million

Project Timeline:
August 29, 2018 – December 2018

Working Hours:
Monday – Friday (No weekends or holidays)
7:00 a.m. – 4:00 p.m.

Construction crews worked to:

  • Install 1.26 miles (6,670 LF) of water pipeline
  • Install 12 fire hydrants
  • Install 181 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the construction notice.
 

outline of previous Florence-Graham Project

Florence-Graham
Nadeau St., 80th St., 81st St., 82nd St., 83rd St., 84th St., 84th Pl., 85th St., Naomi Ave., and Hooper Ave.

Investment:
$4.78 Million

Project Timeline:
Phase I: September 11, 2017 – March 2018
Phase II: November 13, 2017 – May 2018

Working Hours:
Monday – Friday
7 a.m. – 4 p.m.

Construction crews worked to:

  • Install 15,650 ft. of new water pipe
  • Install 411 new service lines
  • Install 33 new fire hydrants

View construction notices:
Part 1 and Part 2
 

outline of Bell Ave. Project

Bell
California Ave., Loma Vista Pl., San Luis Ave., Bell Ave. and Corona Ave.

Project Timeline:
January 4, 2017 – late May 2017

Construction crews worked to:

  • Install 9,000 ft. of new water pipe
  • Install 17 new fire hydrants
  • Install 242 new service lines