Capital Projects

Post
Project map

GRC 2020 General Case (2022-24)

The General Rate Case approved July 29, 2023 invests over $22 million in the Culver City Customer Service Area. The new rates are being invested in your service area’s major water tank upgrades, new pressure relief valves, new main installation, and backup power equipment.

GRC 2023 General Case (2025-27)

The rates proposed for 2025-2027 will provide customers with long-term value by investing over $17.8 million in proactive capital investments and maintenance of local water infrastructure essential to the delivery and treatment of reliable, quality drinking water. Investments in the Culver City Service Area include but are not limited to constructing a new emergency interconnection to improve water supply reliability; upgrading water distribution infrastructure; installing emergency backup generators needed for uninterrupted treatment and delivery of water in the event of a power outage or a natural disaster; replacing aging water mains, meters, and pumps.

Current & Upcoming Projects

Bentley Area Main Replacement (AMR) Water Main Replacement Project

Location:  Bentley Avenue south of Venice to Washington Place and Pigott Avenue from east of Sepulveda to Bentley Avenue in Culver City.

Project Timeline:  September 25, 2023 – January 2024

Construction crews will work to:

  • Install approximately 2,300 LF of 8 & 12” PVC water mains, fire hydrants, fire services, and domestic services in Bentley and Pigott Avenues.

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice.

Wrightcrest Area (Blair Hills) Water Main Replacement Project

Location:  Wrightcrest Dr, Crestview Rd, Ver Halen Ct, Howard View Ct, Leeview Ct, Lenawee Ave, Vicstone Ct, Blairstone Dr, Stoneview Dr, Ivy Way, Perham Dr, La Cienega Blvd.

Project Timeline:  October 2, 2023 – April 2024

Construction crews will work to:

  • Install approximately 7,500 LF of 8″ PVC water mains, fire hydrants, fire services, and domestic services in the Blair Hills Neighborhood.

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice.

Recently Completed Projects 

Westwood Avenue Area Water Main Replacement Project

Location:  Westwood Ave., from Ocean Avenue to Dobson Way, Fairbanks Avenue from Ocean to Studio Drive, Ocean Avenue from Rhoda Way to Cota Street and Virginia Avenue from Overland Avenue to Rhoda Way, Pickford from Ocean to Virginia Avenue

Project Timeline:  February 27, 2023 – July 30, 2023

Construction crews will work to:

  • Install approximately 7,020 LF of 8″ PVC water mains, fire hydrants, fire services, and domestic services.

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice.

Area Water Main Replacement
Culver Park Ave., from Berryman to Slauson Avenue, Diller Avenue from Culver Park to Coolidge Avenue, and Coolidge from Diller Avenue to Port Avenue

Project Timeline:
July 18, 2022 – November 2022

Construction crews will work to:

  • Install approximately 3,900 LF of 8″ PVC water mains, fire hydrants, fire services, and domestic services

View the Construction Notice

Purdue Area Main Replacement
Sepulveda Blvd., Purdue Ave, Woolford St, McDonald St, Slauson Ave, Selmaraine Dr, Etheldo Ave, Emporia Ave, Port Rd, Hammack St

Project Timeline:
Feb. 7, 2022 - November 2022

Working Hours:
Monday-Friday, 8 a.m. – 5 p.m.

Construction crews will work to:

  • Install approximately 10,600 L.F. of 8″ PVC pipe
  • Install 246 new customer service lines

This project will enhance the reliability of drinking water infrastructure in the Culver City area and ensure the residents have safe, reliable water service for their everyday needs.

View the Construction Notice.

Project Map

Sepulveda Area Main Replacement
Sepulveda Blvd., Washington Blvd., to Braddock (as well as 200’ of 12” PVC on Culver Blvd., between Globe and Tuller)

Project Timeline:
April 5, 2021 - October 2021

Working Hours:
Monday-Friday, 8 a.m. – 5 p.m.

Construction crews will work to:

  • Installation of new 16” PVC water mains
  • Install 8 new fire hydrants 
  • Install 47 new customer service lines

This project will enhance the reliability of drinking water infrastructure in the Culver City area and ensure the residents have safe, reliable water service for their everyday needs.

View the Construction Notice.

Northgate Area Main Replacement
Northgate Street from Overland to Drakewood Avenue; Galvin Street from Flaxton to Northgate Street; Flaxton Street from Kinston to Northgate Street; Whitburn Street from Kinston to Drakewood Avenue; Kelmore Street from Kinston to Drakweood Avenue; Overland Avenue from Kelmore to Northgate and a section south of Sawtelle Blvd.

Investment:
$3 Million

Project Timeline:
January 19, 2021 - August 2021

Working Hours:
Monday-Friday, 8 a.m. – 5 p.m.

Construction crews will work to:

  • Install approximately 10,000 LF of new 8” PVC Water Main
  • Install 25 new fire hydrants 
  • Install 220 new customer service lines

This project will enhance the reliability of drinking water infrastructure in the Blanco Park/Culver Crest area and ensure the residents have safe, reliable water service for their everyday needs.

View the Construction Notice.

Baldwin Hills Site Map

Baldwin Hills Water Quality Project/Hetzler Road
Hetzler Road from The State of California Park Gate to Jefferson Blvd.

Investment:
Over $1.5 Million

Project Timeline:
May 11, 2020 – July 30, 2020

Working Hours:
Monday-Friday, 8 a.m. – 4 p.m.
Saturday – Sunday, 9 a.m. – 5 p.m.

In Phase l, Construction crews will work to:

  • Install over 1300’ of new 8” Ductile Water Main
  • Install one new fire hydrant in Hetzler Road from Tompkins Road to Jefferson Blvd

In Phase ll, Construction crews will work to:

  • Install new piping, electrical equipment and pump building and appurtenances

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the construction notice.

outline of Washington Boulevard Project

Washington Boulevard Area Main Replacement 
Washington Boulevard from Helms Avenue to Sentney Avenue

Investment:
$2.019 million

Project Timeline:
Aug. 26, 2019 – April 2020

Project update: As of March 5, 2020, GSWC has installed the new water main and is continuing to run the connections at each intersection off of Washington Boulevard. 

Working Hours:
Washington Boulevard:
Monday-Friday, 9 a.m. – 4 p.m.
Saturday, 9 a.m. – 5 p.m.

Residential Streets:
Monday-Friday, 8 a.m. – 4 p.m.

*Night work may be scheduled for certain construction periods

Construction crews will work to:

  • Install over 4,600 feet of pipe
  • Install 14 hydrants
  • Install 94 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the construction notice.
 

outline of Rudman Area Project[image:403]

Rudman Area Main Replacement 
Construction will take place on the following streets:  Overland Avenue south of Sawtelle to Playa Street; Playa Street to Stevens Avenue; Sawtelle Blvd., west of Malat to Overland Avenue; Rudman Drive, Sawtelle to Playa Street; Greyridge Drive Sawtelle to Playa Street Kingston; Sawtelle Blvd., to Flaxton Street.

Investment:
$1.5 million

Project Timeline:
Aug. 6, 2019 – March 17, 2020

Working Hours:
Residential Streets:
Monday-Friday, 8 a.m.-5 p.m.

Overland Ave., Sawtelle Blvd. and Playa St.:
Monday-Friday, 9 a.m.-4 p.m.

Construction crews will work to:

  • Install over 4,405 LF of pipe
  • Install 97 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the construction notice.

outline of Baldwin Hills Project

Baldwin Hills Storm Drain Replacement 
Jefferson Blvd. at Hetzler Rd. 

Investment:
$867,800

Project Timeline:
Oct. 1, 2018 – November 2018

Working Hours:
7 a.m. – 7 p.m.
Monday to Sunday

Construction crews worked to replace the existing storm drain.

This project increased the capacity of the storm drain and eliminate potential hazards from future storm runoffs.

View the construction notice.
 

outline of Corryne Area Project

Corryne Area Main Replacement
Corryne Place from Slauson Avenue to Sepulveda Blvd.; Slauson Avenue from Selmaraine Drive to Sepulveda Blvd; and Jefferson Blvd. from 405 Freeway to Slauson Avenue.

Investment:
$880,950

Project Timeline:
June 18, 2018 – October 31, 2018

Working Hours:
8 a.m. – 4 p.m. on Corryne Place

9 a.m. – 3 p.m. on Slauson, Jefferson and Sepulveda Blvd.

Construction crews worked to:

  • Install more than o.3 miles (1,771 LF) of new PVC pipe
  • Install water services
  • Install fire hydrants

This project ensures Golden State Water can continue providing reliable water service to local customers.

View the construction notice.
 

outline of Sentney Reservoir Project

Sentney Reservoir Tank Rehabilitation
2920 Sentney Ave.

Investment:
$475,000

Project Timeline:
July 9, 2018 – September 30, 2018

Working Hours:
8 a.m. – 5 p.m.

Construction crews worked to:

  • Apply interior and exterior coating
  • Disinfect
  • Upgrade safety stairs, guard railing and fall restraint system
  • Install cathodic protection system

This project ensures Golden State Water can continue providing reliable water service to local customers.

View the construction notice.
 

outline of Culver Boulevard Project

Culver City
Culver Blvd., Wagner St. and Coombs Ave.

Project Timeline:
September 5, 2017 – late April 2018

Working Hours:
8 a.m. – 5 p.m.

Construction crews will work to:

  • Replace existing water pipes
  • Install new fire hydrants and services
  • Install new service lines

View the construction notice.
 

outline of Globe Avenue Project

Globe Area
Glove Ave., Herbert St., Albright Ave., and Huntley Alley

Project Timeline:
May 1, 2017 – early April 2018

Working Hours:
8 a.m. – 5 p.m. *residential streets
9 a.m. – 3 p.m. *arterial streets

Construction crews will work to:

  • Replace existing water pipes
  • Install new fire hydrants and services
  • Install new service lines

View the construction notice.
 

outline of Huntley Avenue Project

Huntley Ave.
Franklin Ave. and Huntley Pl.

Project Timeline:
January 30, 2017 – March 31, 2017

Working Hours:
N/A

Construction crews worked to:

  • Install new water pipes
  • Install new fire hydrants
  • Install new service lines