Capital Projects

Post

2023 General Rate Case (2025-27)

The rates adopted for 2025-2027 will provide customers with long-term value by investing over $11.9 million in needed capital investments and maintenance of local water infrastructure essential to the reliable production, treatment, and delivery of quality water.

Investments in the San Gabriel Service Area include, but are not limited to, water distribution projects, construct  a new reservoir, construct a booster station and replace another booster station, construct a new well, systemwide technology to monitor and control the water system, and emergency generators needed for uninterrupted production, treatment and delivery of water in the event of power outages, natural disasters and to reduce the strain on the electrical grid, and the replacement of aging water mains. As part of our commitment to reliability and public safety, Golden State Water proactively invests in upgrading and maintaining its fire hydrants. 

For frequently asked questions about the rate-making process, click here.

Learn about the infrastructure investments in the water system serving your community’s homes and businesses: 2023 GRC Infrastructure Investments - San Gabriel.

Current & Upcoming Projects

Recently Completed Projects

Saxon Plant – Well Replacement, Reservoir and Booster Station

Location: 409 E Saxon Ave, San Gabriel, CA, 91776

Project Timeline: June 21, 2023 – Mid-November 2023

Working Hours: Monday – Friday (No weekends or holidays) 7:00 a.m. – 5:00 p.m. However, there will be times during the construction period when around-the-clock (24 hours a day, 7 days a week) operations will be necessary.

Construction crews will work to: 

  • Demolish existing building. Construct a 0.75 MG reservoir.
  • Drill and equip a replacement well for Saxon Well #3, consolidate chlorine buildings and replace drain line due to leaks.
  • Construct a new booster station at the Saxon Plant inside a building, replace the MCC and PLC and increase service from Southern California Edison.

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice.

outline of Lynrose Street Project

South Arcadia Main Replacement
Lynrose St., between Florinda Ave. and Tyler Ave.; Daneswood Dr., between Florinda Ave. and Tyler Ave.; and Alley south of Live Oak Ave., Tyler Ave. to the Savers parking lot

Investment:
$970,000

Project Timeline:
September 17, 2018 – January 2019

Working Hours:
Monday – Friday (No weekends or holidays)
7 a.m. – 5 p.m.

Construction crews worked to:

  • Install 400 LF of pipeline
  • Install 4 fire hydrants
  • Install 112 service lines

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the construction notice.
 

outline of Graves Avenue Project

Graves Main Replacement
Graves Ave. from Del Mar Ave. to Eckhart Ave.

Investment:
$490,000

Project Timeline:
September 24, 2018 – November 2018

Working Hours:
7 a.m. – 4 p.m.

Construction crews worked to:

  • Install 1,200 LF of pipeline
  • Install one fire hydrant
  • Install 49 services

This project improves the distribution system and ensures Golden State Water can continue providing reliable water service to local customers.

View the construction notice.
 

outline of Garvey Avenue Project

Rosemead
Garvey Ave. and Delta Ave. 

Project Timeline:
June 26, 2017 – September 28, 2017

Construction crews worked to:

  • Install water pipe extension
  • Install new service lines to the business
  • Install fire service to the business

View the construction notice.
 

outline of Monterey Park and Rosemead Project

Monterey Park and Rosemead
New Ave. between Whitmore St. and Hellman Ave. 

Project Timeline:
June 26, 2017 – September 20, 2017

Construction crews worked to:

  • Replace aged water pipe
  • Install new service lines
  • Install fire hydrants

View the construction notice.
 

outline of Longden Avenue Project

Irwindale
Longden Ave. between Peck Rd. and Live Oak Ave.

Project Timeline:
April 17, 2017 –  June 30, 2017

Construction crews worked to:

  • Replace aged water pipe
  • Install new service lines
  • Install fire hydrants

View the construction notice.
 

outline of Rosemead Gladys Avenue Project

Rosemead
Gladys Ave. and Charlotte Ave. north of Graves Ave.

Project Timeline:
March 13, 2017 – June 23, 2017

Construction crews worked to:

  • Replace aged water pipe
  • Install new service lines
  • Install fire hydrants

View the construction notice.
 

outline of Temple City and El Monte Project

Temple City and El Monte
Halifax Rd., Doreen Ave., Key West Ave., Arden Dr., Miloann St., Hallowell St., Freer St. and Lower Azusa Rd.

Project Timeline:
October 17, 2016 – June 5, 2017

Construction crews worked to:

  • Replace aged water pipe
  • Install new service lines
  • Install fire hydrants

View the construction notice.
 

outline of Rosemead Isabel Avenue Project

Rosemead
Isabel Ave. south of Emerson Pl.

Project Timeline:
January 3, 2017 – February 17, 2017

Construction crews worked to:

  • Replace approximately 1,000 ft. of aged water pipe
  • Install new service lines
  • Install fire hydrants

View the construction notice.