Capital Projects

Post

GRC 2020 General Case (2022-24)

The General Rate Case approved June 29, 2023, invests over $8 million in the Wrightwood Customer Service Area. The new rates are being invested in your community’s chlorine analyzers, new main installation, reservoir expansion, and backup power equipment.

GRC 2023 General Case (2025-27)

The rates proposed for 2025-2027 will provide customers with long-term value by investing over $7.3 million in proactive capital investments and maintenance of local water infrastructure essential to the delivery and treatment of reliable, quality water. Investments in the Wrightwood Service Area include, but are not limited to, water distribution projects, seismic and structural improvements to a reservoir, construct a new reservoir, and improvements to a water treatment plant and well treatment system, and the replacement of aging water mains, pumps, and purification and safety equipment.

Current & Upcoming Projects

Mojave Scenic Drive Main Replacement Project

Location: The new pipelines will be installed on the Mojave Scenic Drive between Sheep Creek Drive and East Canyon Drive in Wrightwood Area of San Bernardino County, California.

Project Timeline:
May 2024 – June 2024

Working Hours:
8:00 a.m. – 4:30 p.m.

Construction crews will work to:

  • Install new 6’, 8” and 12” PVC water mains, fire hydrants, and domestic water services.

This project will ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice.

Recently Completed Projects

Lone Pine Reservoir Demolition

Location: Lone Pine Canyon Reservoir

Project Timeline:
November 3, 2022 – Mid-December 2022

Working Hours:
8:00 a.m. – 5:00 p.m.

Construction crews will work to:

  • Demolish existing steel reservoir and related equipment

View the Construction Notice.

Wrightwood Fire Hardening Project

Location: Evergreen Plant, Bobolink Plant, Buford Well No. 5, Orchard Plant, Ceder Plant, Health Creek Plant No. 4 and No. 7

Project Timeline:
December 2021 – April 2022

Working Hours:
7:00 a.m. – 5:00 p.m.

Construction crews will work to:

  • Install concrete panels 
  • Install concrete posts

View the Construction Notice.

outline of Wrightwood Project

Wrightwood
Cardinal Rd., Flume Canyon Dr., Swallow Hill Dr., Logwood Dr., Redstart Dr., Pine Creek Dr., Bluejay Dr., Goldhill Dr., Bobolink Dr., and Rapid Grove Dr.

Project Timeline:
June 19, 2017 – October 17, 2017

Working Hours:
8 a.m. – 5 p.m.

Construction crews worked to:

  • Install approximately 5,800 ft. of water pipe
  • Install 43 new service lines
  • Install 4 fire hydrants

View the Construction Notice.
 

outline of Wrightwood Project

Wrightwood
Spruce St., Mill Rd., Acorn Dr., Pine St., Cedar St., Evergreen Rd., Edna St., Lark Rd., Robin Rd., Robin Ln., Oriole Rd., Mockingbird Rd., Eagle Rd., Partridge Rd., and Pheasant Rd., Spruce St., Mockingbird Rd., Eagle Rd., & Partridge Rd., within the parameters of Mill Rd., Evergreen Rd., Cedar St., and Pheasant Rd.

Project Timeline:
May 9, 2017 – early November 2017

Construction crews worked to:

  • Install approximately 18,000 ft. of water pipe
  • Install 233 new service lines
  • Install 22 fire hydrants

View the Construction Notice.